Energy Ministry Orders Bangchak Refinery Shutdown Until Jan 8
Energy Ministry orders Bangchak's Phra Khanong refinery in Bangkok to shut down until Jan. 8, 2027, following an explosion in a hydrocracking unit. The company must repair damage, submit an independent incident report within seven days, and
The Ministry of Energy has ordered Bangchak to temporarily suspend refinery operations until January 8, 2027, following an explosion. The company must urgently repair damaged equipment and submit an incident report to the Department of Energy Business within three days.
At a 4:00 PM press conference on November 27, 2026, at Bangchak's Phra Khanong refinery in Bangkok, Ministry Permanent Secretary Thitiphassorn Chotidechanan, Department of Energy Business Deputy Director-General Chat Chai Khunlohit, Bangchak Corporation Deputy Managing Director Anuwat Rungrueangrattanakul, and Factory Department officials announced the inspection results of yesterday afternoon's explosion.
Thitiphassorn disclosed that Energy Minister Ekkanat Promphan had directed the Department of Energy Business and officials to inspect the oil and LPG storage areas after yesterday's fire. The site had previously been inaccessible, but Bangchak cooperated today by opening the area for inspection.
The fire occurred in Unit 4, a hydrocracking unit within the distillation process. Equipment there falls under the Factory Department's jurisdiction per the Factory Act, as it involves industrial machinery. The Ministry of Industry tasked the Factory Department to jointly inspect with the Department of Energy Business.
The Factory Department issued an order under Section 39 for Bangchak to halt operations until January 8, 2027, and to rectify violations under the Factory Act to ensure safety. Once compliance is complete, officials will re-inspect. If safety and regulations are fully met, the suspension will be lifted; otherwise, the shutdown will be extended.
The Department of Energy Business issued an order under Section 54 of the Fuel Control Act B.E. 2542, requiring Bangchak to submit a written incident report detailing damage to oil tanks, piping, and equipment within seven days. The report must be prepared by a certified independent third-party inspector approved by the department.
Additionally, Bangchak must conduct a Hazard Analysis to assess heat and pressure impacts on storage tanks, piping, and control systems for oil and LPG. Any damaged equipment must be reported immediately for suspension and repair before reuse.
The Department of Energy Business will monitor operations, incident modeling, and equipment checks to ensure oil storage, LPG storage, and pipeline systems remain unaffected and safe before allowing transport or operations to resume.
Regarding refinery oversight, the Department of Energy Business Deputy Director-General clarified that the process within