Yasothon PAO Flags Rushed 9.3M Baht Road Project
Yasothon's Provincial Administrative Organization has raised concerns over a 9.3-million-baht road project in Kud Chum district after the contractor completed 60% of the work in just 19 days, with handover occurring on a public holiday. The PAO warned that such accelerated construction may compromise structural quality and has ordered strict monitoring throughout the two-year warranty period. Officials have also requested all project documents for a deeper investigation into potential irregularities.
YASOTHON — The Anti-Corruption Division of the Yasothon Provincial Administrative Organization (PAO) carried out a second on-site follow-up of a project to widen and resurface Soi Municipality 18, under the responsibility of the Kud Chum Phatthana Subdistrict Municipality in Kud Chum district, Yasothon province. The project has a budget of 9,324,000 baht (actual disbursement 9,166,249.13 baht) and a contract period of 180 days.
This second inspection followed significant concerns about construction speed and acceptance procedures identified during the first site visit on July 21, 2026 (BE 2569). At that time, only six days remained before the contract expiry on July 27, yet progress stood at just 40%. The municipality had prepared to grant a seven-day extension, citing erroneous design plans, but the PAO objected, warning this could constitute undue favor to the contractor to avoid daily penalties. The PAO recommended suspending the extension pending consultation with the State Audit Office and the Provincial Treasury.
During the latest follow-up in November 2026, inspectors found the remaining 60% of work — including drainage pipes, culverts, and 106 catch basins — had been rushed to completion within 19 days, with formal acceptance taking place on a Saturday, a public holiday.
The Kud Chum Phatthana Subdistrict Municipality explained that staff had supervised work around the clock and affirmed all procedures complied with regulations, adding that budget disbursement to the contractor had been completed.
Nevertheless, the Yasothon PAO issued three key observations:
1. Official duty orders in writing from a superior, clearly stating the necessity, are required for staff working on public holidays. 2. Accelerating such a large volume of construction in a short timeframe may compromise road structural standards and durability; officials must strictly enforce the contract throughout the two-year defect liability period. 3. The PAO has requested all project documents from the municipality for further analysis and in-depth investigation under its statutory authority.