SRT Board Orders Review of Thai-China High-Speed Rail PPP Plan
The State Railway of Thailand board has ordered a review of the PPP investment plan for the Thai-China high-speed rail Bangkok-Nong Khai project before resubmitting it for cabinet approval. Phase 1 service is now projected to launch around mid-2032, with preliminary fares of 1,400 baht for the full Bangkok-Nong Khai route. Tenders for the Bang Sue-Don Mueang and Ban Pho-Phra Kaeo sections are targeted for 2028.
SRT Governor Anant Phonnimdaeng disclosed that at the SRT board meeting on November 19, 2026, the board instructed SRT and its consultants to update the PPP investment study for the Thai-China high-speed rail Bangkok-Nong Khai project, covering both Phase 1 and Phase 2. The study was originally completed in 2025 and must be revised before being presented again to the board, then to the Ministry of Transport and the Cabinet. Key review areas include construction timelines aligned with current plans, funding structure, private-sector returns, and assumptions on fares, ridership, revenue, and costs to thoroughly assess project viability.
For Phase 1, civil works are expected to finish in 2031, followed by installation of electrical, signaling, and overhead power systems. If system testing begins in early 2032, it will take nearly six months, plus staff training and driver testing, putting the projected service launch around mid-2032.
On fares, consultants set prices above private car travel but below air travel, with a 120 baht base fare plus distance-based charges. Preliminary estimates put Bangkok Apiwat-Nong Khai at about 1,400 baht, Bangkok-Khon Kaen at 1,080 baht, and Bangkok-Nakhon Ratchasima at 695 baht, all still subject to review. The board emphasized verifying the feasibility of revenue and cost assumptions.
Contract 4-1 (Bang Sue-Don Mueang) is undergoing scope evaluation and reference price preparation after the appointment of a price assessment committee. Work quantities and estimated prices must be finalized before submission to the SRT board and Cabinet. This section is complex, requires Chinese design standards, and must clearly separate scope related to the high-speed rail link connecting three airports, so the construction budget cannot yet be specified. The previous estimate of around 22 billion baht from 2-3 years ago must be updated, and detailed assessment is unlikely to finish by December 2026.
For Contract 4-5 (Ban Pho-Phra Kaeo), consultants have begun work and are preparing geotechnical drilling to develop work quantities and construction details before determining the procurement approach and launching tenders. Preliminary expectations target commencement in early 2027. The overall plan remains within the original framework, and SRT confirms it will tender both contracts by 2028.